Data center water-supply audits
Governors and counties are pausing data center approvals until power grids and water supplies are audited. That raises a practical question: what should a water-supply audit actually include? This page is for two audiences — neighbors and private well owners who speak at hearings, and the hydrogeologists, labs and consultants who do the technical work. For how much water data centers use and which permits apply, start with the data centers and water overview. For your own well baseline, see data centers and water testing.
This is general information, not legal, engineering or hydrogeologic advice. Audit requirements differ by state and locality, and they change. Confirm what your county, groundwater district or state agency actually requires before you rely on a checklist. Nothing here can tell you whether any well's water is safe to drink.
On a private well? Focus on sections 2 and 3 below (aquifer capacity and baseline monitoring of nearby wells), and start your own record with document your well before construction.
On city or county water? Focus on sections 1 and 6 (source, peak volumes, drought curtailment, who can read the results). Your utility's contract with the data center is where those answers live. To check what's at your faucet (CCR first, then a certified-lab spot-check), see how to test city tap water.
Who to ask in your state: data center water policy by state.
Area context for a household (not a substitute for an audit): Household Water Risk Score.
Why audits are in the news
"Pause until audited" is becoming a policy tool. The audits named in press releases often mix grid, tax and water questions. This page focuses on the water-supply side: sources, volumes, aquifer capacity, cooling technology, discharges and monitoring.
Texas (2026)
On Aug. 3, 2026, Gov. Greg Abbott directed the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) to complete a comprehensive verification and audit of data centers advancing through ERCOT's interconnection process before approving more grid connections. His letter asked those agencies to collect, among other items, projected annual and peak water consumption, anticipated water sources, whether projects bring or reuse their own water rather than drawing on community supplies, and cooling technology (air-cooled, closed-loop or other water-efficient systems).1
ERCOT later said it aimed to file its Batch Zero verification and community-impact reports around Dec. 10, 2026, covering hundreds of large-load projects, most of them data centers.23
Separately, Abbott directed the Texas Water Development Board (TWDB) on water-use reporting and partnership with ERCOT on the audit, and on Sept. 21, 2026, directed the Texas Commission on Environmental Quality (TCEQ) to halt permits sought by data center projects until the ERCOT audit is complete. TCEQ said it paused air and water permits and authorizations for infrastructure that directly supports data centers while that audit proceeds.45
After the Nov. 3, 2026 election, governor-elect Gina Hinojosa — who takes office Jan. 19, 2027 — pledged during the campaign to issue a moratorium on data center approvals until the Legislature passes stronger protections. The Texas Tribune reported that her priorities included protecting community water supplies, limiting nondisclosure agreements that hide project details, and giving local communities more say. DatacenterDynamics summarized her call to extend the pause beyond the current audit window until new laws are in place. Campaign pledges are not yet law; wording here follows those published accounts.67
Other examples
- Utah (HB 76): new large data centers that plan to use 75 acre-feet a year or more must report before construction and every year after. The Division of Water Rights publishes annual withdrawals. Reporting is not the same as a pre-approval hydrogeologic audit, but it makes volumes public.8
- Marion County, Florida (Sept. 15, 2026): county commissioners approved a 12-month pause on accepting or approving large commercial data centers at 50 megawatts peak demand or more. Staff are directed to study Floridan Aquifer withdrawals, water and wastewater capacity, springs and springsheds, and cooling practices (including reclaimed water and closed-loop or air-cooled systems) before writing new land-development rules.910
- State reporting elsewhere: New Jersey and Virginia have new disclosure rules for data center water or the potable and reclaimed water utilities sell them. Details are on the overview page.11
For every state and county rule we track, with its status and the public agency contact to ask for the latest update, see data center water policy by state.
For consumers, well owners and neighbors: what to ask for
You do not need to design the study yourself. At planning hearings, utility board meetings and public-comment periods, ask whether each item below is in the record — and whether the public can read it without an NDA.
1. Source of the water
- Will the facility buy municipal (city or public-system) water, pump its own groundwater, use reclaimed wastewater, or mix sources? CRS cites an estimate that public systems supplied most U.S. data-center on-site water in 2025, but on-site wells exist in documented cases.11
- Peak daily volume and annual volume for make-up water, not just a marketing "gallons per day" line.
- A drought curtailment plan: who gets cut first when the utility or aquifer is stressed?
More background: Will a nearby data center affect my well? and who regulates big groundwater pumpers.
2. Local supply and aquifer capacity
Ask for a capacity study that looks at cumulative withdrawals — the project plus other large users and existing private wells — not only the project's own pipe. USGS describes how pumping creates a cone of depression that can interfere with nearby wells when cones overlap.1415 Whether a specific site affects you depends on the aquifer and rates; NGWA notes that in some aquifers the neighbor effect is small or hard to measure.13
3. Baseline monitoring for nearby wells
Before construction, ask whether the applicant will fund (or the county will require) a monitoring network that records:
- Static water levels and, where practical, quality in a sample of nearby domestic wells
- Observation wells in the same aquifer interval the project would use
- A public schedule for posting results
A one-time "will serve" letter from a utility does not replace that. For what you can measure on your own well, use Data centers and water testing and document your well before construction.
4. Cooling technology — with verification
Ask which cooling design is proposed (evaporative / cooling towers, hybrid, air-cooled, closed-loop) and how water-efficiency claims will be verified after the facility is built. Abbott's Texas audit letter specifically asked for cooling-technology detail.1 Evaporative systems use more water on site; air and closed-loop systems use little on site but usually more electricity, which has its own water footprint at power plants. LBNL discusses that tradeoff.12 See also How data centers treat cooling water.
5. Discharge and blowdown pathway
Where does concentrated cooling water (blowdown) go — city sewer under a pretreatment agreement, or a direct discharge needing an NPDES permit? CRS summarizes typical pathways and constituents.11 Construction stormwater and wetland permits can also apply.
6. Who pays, and who can read the results
Ask in writing:
- Who pays for monitoring wells, lab work and annual reports?
- Are volumes and monitoring results public, or locked behind NDAs?
- What happens if levels or quality in neighboring wells change after operations start?
Utah's published annual reports are one model for making withdrawals visible.8 Hinojosa's campaign priorities, as reported by the Texas Tribune, specifically flagged NDAs that make it harder for the public to track projects.6
For third-party auditors: a practical scope checklist
This section is for hydrogeologists, environmental consultants, certified labs and engineers retained by a developer, a county, a utility or a citizens' group. It is a scope outline, not a standard of care. Follow your state's consumptive-use / water-use permit guidance and your professional license rules.
Desktop review
- Existing water rights, certificates, groundwater conservation district rules or consumptive-use permits (CUPs)
- Utility capacity letters, rate schedules and drought contingency plans
- Prior CUP or high-capacity well files for the same aquifer and competing users
- State reporting obligations that already apply (for example Utah HB 76 thresholds)8
- Discharge / pretreatment requirements and any existing NPDES or industrial-user permits11
- Zoning, site-plan and economic-development agreements that mention water volumes or NDAs
Field and aquifer work
When the project would pump groundwater, or when municipal supply depends on wells in the same aquifer:
- Aquifer-test design with controlled pumping rates, drawdown and recovery measurements. USGS Techniques of Water-Resources Investigations Book 3, Chapter B1 covers aquifer-test design, observation and data analysis.16 EPA's suggested operating procedures for aquifer pumping tests are a practical field reference.17
- Method selection and field procedure standards such as ASTM D4043 (selecting an aquifer-test method) and ASTM D4050 (withdrawal/injection well testing for hydraulic properties) — use the current published editions.1819
- Observation wells completed in the same aquifer interval, plus nearby domestic wells (with owner permission) for interference checks
- Stream, spring or wetland gauges where the aquifer is connected to surface water (Marion County's study list explicitly includes springs and springsheds)9
- Seasonal baselines: levels and selected chemistry before construction, not only a single site visit
Water balance (cooling)
Document make-up, evaporation, blowdown and cycles of concentration. DOE's cooling-tower best-management practice calls for conductivity control, flow meters on make-up and blowdown, and logs of volumes and cycles so leaks and losses can be spotted.20 Tie claimed peak and annual gallons to this balance, not to an unaudited brochure number.
Water quality interfaces
- Make-up chemistry for scaling, corrosion and pretreatment needs when the source is groundwater or reclaimed water11
- Blowdown constituents expected under the discharge pathway (dissolved solids, treatment chemicals, corrosion metals)11
- Legionella water-management programs for cooling towers are an operator responsibility under public-health guidance (CDC / ASHRAE). Note the interface in the audit, but do not treat a WMP as a substitute for a supply-capacity study.21
Cumulative impact and domestic-well interference
Evaluate the project's withdrawal together with other large users. USGS cone-of-depression and well-interference concepts are the physical basis; state CUP guidance often sets the review radius and significance tests.1413 Say clearly what radius was studied, which wells were inventoried, and what was not modeled.
Independence and reporting
- Disclose who hired you and any conflicts
- Separate confidential business details from public volumes, sources and monitoring plans whenever the client or the agency allows
- State methods, assumptions, data gaps and uncertainty in plain terms a planning board can follow
- Prefer formats the public can retrieve later (agency portals, not only closed hearing binders)
What is not enough
These items may be necessary paperwork, but they are not a water-supply audit by themselves:
- A one-page utility "will serve" or capacity letter with no peak/annual volumes, no drought plan and no cumulative look at other demand
- Unaudited marketing gallons (or "water positive" claims) with no meter plan or third-party verification
- NDAs that hide contracted volumes from the public while asking a county to rezone or approve a site plan6
- Cooling-technology adjectives ("efficient," "sustainable") without naming evaporative vs closed-loop/air and without a verification path1
- A grid-only or tax-incentive audit that never opens the water-source and aquifer questions Texas and Marion County have put on their study lists19
Frequently asked questions
Is a state "pause until audited" the same as a hydrogeologic study? Not necessarily. Texas's 2026 directives combine grid verification, community-impact questions, tax incentives and water-use reporting. A local moratorium study (as in Marion County) can be more aquifer-focused. Read the actual scope.19
If the data center will only buy city water, do neighbors still need an audit? City water still comes from somewhere — often wells or surface reservoirs that serve homes too. Ask for peak/annual volumes, the utility's drought plan and whether the contract can curtail the facility before residential customers. CRS and utility examples on the overview help frame those questions.11 For what's in the glass at your own faucet, see how to test city tap water — that check is separate from an aquifer or utility-capacity audit.
What should I do for my own well while agencies audit? Record a baseline now: static water level and a certified lab panel. Details are in Data centers and water testing.
Where do labs and well contractors fit? Labs run the chemistry. Licensed well contractors measure levels and yields and may install monitoring wells. Hydrogeologists design aquifer tests and interference analyses. Our directory lists licensed well pros from official state lists where we cover; county pages list testing contacts.
Related guides
- Data centers and your water: FAQ (safe nearby? bill?)
- Household Water Risk Score (area context vs audit vs lab test)
- How to test city tap water (CCR + certified-lab spot-check)
- Data center water policy by state: reporting, pauses, and who to ask
- Data centers and water: how much they use, where it comes from, and the rules
- Will a nearby data center affect my well?
- Data centers and water testing
- How data centers treat cooling water
- Who regulates big groundwater pumpers?
- How to document your well before nearby construction or heavy pumping
- Who regulates private wells?
Where to get tested and treatment options
-
Office of the Texas Governor, letter from Gov. Greg Abbott to PUCT Chairman Thomas Gleeson and ERCOT CEO Pablo Vegas, Aug. 3, 2026 (PDF), directing a comprehensive verification and audit including projected water consumption, sources and cooling technology. https://gov.texas.gov/uploads/files/press/Thomas_Gleeson_Pablo_Vegas_Data_Centers_Directive_Letter_to_PUCT_ERCOT_August_2026_.pdf ↩↩↩↩↩
-
Ethan Howland, "ERCOT aims to complete Texas governor's data center audit by December," Utility Dive, Aug. 21, 2026. https://www.utilitydive.com/news/ercot-texas-puc-data-center-audit/828472/ ↩
-
ERCOT, "Good Cause Exceptions for PGRR 145 Batch Zero Verification and Audit Process / Community Impact Review Process" presentation to PUCT, Aug. 20, 2026 (PDF), stating a Dec. 10 filing goal for verification and community-impact reports. https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf ↩
-
Office of the Texas Governor, "Governor Abbott Directs TCEQ To Halt Data Center Permits," Sept. 21, 2026. https://gov.texas.gov/news/post/governor-abbott-directs-tceq-to-halt-data-center-permits ↩
-
Stephen Pederson, "Gov. Abbott orders TCEQ to pause environmental permits for data centers until audit is complete," Texas Public Radio / Houston Public Media, Sept. 21, 2026. https://www.tpr.org/news/2026-09-21/gov-abbott-orders-tceq-to-pause-environmental-permits-for-data-centers-until-audit-is-complete ↩
-
Emily Foxhall, "Gina Hinojosa won the governor's race. What happens to Texas data centers now?," Texas Tribune, Nov. 4, 2026. https://www.texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/ ↩↩↩
-
"Texas governor-elect Gina Hinojosa promises continued data center moratorium, further legislation," DatacenterDynamics, Nov. 2026. https://www.datacenterdynamics.com/en/news/texas-governor-elect-gina-hinojosa-promises-continued-data-center-moratorium-further-legislation/ ↩
-
Utah Division of Water Rights, "Large Data Center Water Use Reporting." https://waterrights.utah.gov/data-centers/ ↩↩↩
-
"Marion County pauses large commercial data centers for a year with a 50-megawatt cutoff on who still gets through," 352today, Sept. 2026 (reporting the Sept. 15, 2026 Board of County Commissioners votes and the ordinance study list covering Floridan Aquifer withdrawals and cooling practices). https://352today.com/news/257752-marion-county-pauses-large-commercial-data-centers-for-a-year-with-a-50-megawatt-cutoff-on-who-still-gets-through/ ↩↩↩↩
-
"Marion County approves 12-month moratorium on large-scale data centers," Ocala-News.com, Sept. 16, 2026. https://www.ocala-news.com/2026/09/16/marion-county-approves-12-month-moratorium-on-large-scale-data-centers/ ↩
-
Congressional Research Service, "Data Centers and Water: Frequently Asked Questions" (R49057, July 31, 2026). https://www.congress.gov/crs-product/R49057 ↩↩↩↩↩↩↩
-
Shehabi et al., Lawrence Berkeley National Laboratory, "2024 United States Data Center Energy Usage Report" (LBNL-2001637, December 2024), sections 4–5. https://eta-publications.lbl.gov/sites/default/files/2024-12/lbnl-2024-united-states-data-center-energy-usage-report_1.pdf ↩
-
National Ground Water Association, "FAQ Sheet: Data Centers and Groundwater" (2026) (PDF). https://www.ngwa.org/docs/default-source/default-document-library/faq-data-centers-and-gw_final.pdf ↩↩
-
USGS, "The mutual interference of artesian wells on Long Island, New York." https://www.usgs.gov/publications/mutual-interference-artesian-wells-long-island-new-york ↩↩
-
USGS Water Science School, "Why do water levels in wells rise and fall?" https://www.usgs.gov/water-science-school/science/water-qa-why-do-water-levels-wells-rise-and-fall ↩
-
Stallman, R.W., USGS Techniques of Water-Resources Investigations, Book 3, Chapter B1, "Aquifer-Test Design, Observation and Data Analysis" (PDF). https://pubs.usgs.gov/twri/twri3-b1/pdf/twri_3-B1_a.pdf ↩
-
U.S. EPA, "Ground Water Issue: Suggested Operating Procedures for Aquifer Pumping Tests" (PDF). https://www.epa.gov/sites/default/files/2015-06/documents/sopaqu.pdf ↩
-
ASTM D4043, "Standard Guide for Selection of Aquifer Test Method in Determining Hydraulic Properties by Well Techniques" (current edition; paywalled on ASTM's site). https://www.astm.org/d4043.html ↩
-
ASTM D4050, "Standard Test Method for (Field Procedure) for Withdrawal and Injection Well Testing for Determining Hydraulic Properties of Aquifer Systems" (current edition). https://www.astm.org/d4050-20.html ↩
-
U.S. DOE FEMP, "Best Management Practice #10: Cooling Tower Management." https://www.energy.gov/cmei/femp/best-management-practice-10-cooling-tower-management ↩
-
CDC, "Controlling Legionella in Cooling Towers." https://www.cdc.gov/control-legionella/php/toolkit/cooling-towers-module.html ↩