 "last_checked": "2026-11-06",
 "rows": [
  {
   "id": "tx-ercot-audit",
   "state": "TX",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Texas (ERCOT / PUCT)",
   "policy_type": "moratorium_pause",
   "summary": "Gov. Abbott's Aug. 3, 2026 directive pauses ERCOT grid connections for large data centers until a verification audit that asks for water sources, annual and peak water use and cooling technology; ERCOT plans to publish the report on or before Dec. 10, 2026.",
   "status": "in_force",
   "agency_name": "Electric Reliability Council of Texas (ERCOT) - Data Center Impact RFI",
   "agency_url": "https://www.ercot.com/about/legal/data-center-impact-rfi",
   "public_contact_email": "DataCenterImpact@ercot.com",
   "public_contact_notes": "ERCOT lists this address for questions about the RFI. RFI deadline was Oct. 12, 2026; individual company answers are confidential.",
   "sources": "https://www.ercot.com/about/legal/data-center-impact-rfi https://gov.texas.gov/uploads/files/press/Thomas_Gleeson_Pablo_Vegas_Data_Centers_Directive_Letter_to_PUCT_ERCOT_August_2026_.pdf https://www.utilitydive.com/news/ercot-texas-puc-data-center-audit/828472/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_phone": ""
  },
  {
   "id": "tx-tceq-pause",
   "state": "TX",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Texas (TCEQ)",
   "policy_type": "moratorium_pause",
   "summary": "Per the governor's Sept. 21, 2026 directive, TCEQ says it has paused air and water permits and authorizations for infrastructure directly supporting data centers until the ERCOT audit is complete, and took its STEERS e-permitting system down to screen data center filings.",
   "status": "in_force",
   "agency_name": "Texas Commission on Environmental Quality (TCEQ)",
   "agency_url": "https://www.tceq.texas.gov/downloads/response/tceq-response-gov-abbott-dc-directive.pdf",
   "public_contact_email": "pep@tceq.texas.gov",
   "public_contact_notes": "Confirmed 2026-11-06 by Calen Roome (TCEQ External Relations): pep@tceq.texas.gov is the correct public contact for data center permit questions; OK to list publicly. Status/search: https://permit-search.tceq.texas.gov/. Watchdog Public Citizen reported permits still moving after the directive; TCEQ said those stormwater permits were then suspended.",
   "sources": "https://www.tceq.texas.gov/downloads/response/tceq-response-gov-abbott-dc-directive.pdf https://www.tceq.texas.gov/agency/steers-down https://www.tceq.texas.gov/agency/directory/emailboxes.html https://www.texastribune.org/2026/10/20/data-center-permits-tceq-abbott-texas-pause/ https://permit-search.tceq.texas.gov/",
   "update_contact_requested": "yes",
   "last_checked": "2026-11-06",
   "public_contact_phone": ""
  },
  {
   "id": "tx-twdb-survey",
   "state": "TX",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Texas (TWDB)",
   "policy_type": "reporting",
   "summary": "The TWDB annual Water Use Survey is mandatory for recipients, and the governor's Sept. 14, 2026 directive tells TWDB to enforce it against data centers (referral to prosecutors; nonfilers ineligible for Chapter 11 water-right permits).",
   "status": "in_force",
   "agency_name": "Texas Water Development Board (TWDB) - Water Use Survey Team",
   "agency_url": "https://www.twdb.texas.gov/waterplanning/waterusesurvey/",
   "public_contact_email": "waterusesurvey@twdb.texas.gov",
   "public_contact_phone": "(512) 463-7952",
   "public_contact_notes": "Hotline staffed weekdays 7:30-12:30 and 1:30-4:30 Central.",
   "sources": "https://www.twdb.texas.gov/waterplanning/waterusesurvey/ https://gov.texas.gov/news/post/governor-abbott-directs-twdb-to-penalize-data-center-reporting-failures https://insideclimatenews.org/news/03092026/texas-no-mailing-list-for-data-centers/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "tx-hinojosa-pledge",
   "state": "TX",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Texas (governor-elect)",
   "policy_type": "moratorium_pause",
   "summary": "Governor-elect Gina Hinojosa (takes office Jan. 19, 2027) pledged during the campaign to keep data center approvals paused until the Legislature passes stronger protections, including for community water supplies and limits on NDAs. A campaign pledge, not law.",
   "status": "campaign_pledge",
   "agency_name": "Office of the Governor-elect (no agency yet)",
   "public_contact_notes": "No official transition contact found. Watch the 90th Legislature (convenes January 2027) for bills.",
   "sources": "https://www.texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/ https://www.datacenterdynamics.com/en/news/texas-governor-elect-gina-hinojosa-promises-continued-data-center-moratorium-further-legislation/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "tx-gcds",
   "state": "TX",
   "jurisdiction_level": "district",
   "jurisdiction_name": "Texas groundwater conservation districts",
   "policy_type": "withdrawal_permit",
   "summary": "A data center that pumps its own groundwater is usually permitted by the local groundwater conservation district, which sets spacing and production rules and decides which applications get a hearing.",
   "status": "in_force",
   "agency_name": "Texas Water Development Board - Groundwater Conservation Districts map",
   "agency_url": "https://www.twdb.texas.gov/groundwater/conservation_districts/",
   "public_contact_notes": "Each district has its own manager and board; find yours on the TWDB map. Not every county has a district.",
   "sources": "https://www.twdb.texas.gov/groundwater/conservation_districts/ https://texas.public.law/statutes/tex._water_code_section_36.114",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "ut-hb76",
   "state": "UT",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Utah",
   "policy_type": "reporting",
   "summary": "HB 76 (effective July 1, 2026): new data centers over 10,000 sq ft planning 75 acre-feet a year or more must file a pre-construction report and annual water-use reports; the state publishes annual withdrawals by Sept. 1, and land use authorities must notify the Division before approving one.",
   "status": "in_force",
   "agency_name": "Utah Division of Water Rights",
   "agency_url": "https://waterrights.utah.gov/data-centers/",
   "public_contact_email": "waterrights@utah.gov",
   "public_contact_phone": "801-538-7240",
   "public_contact_notes": "Confirmed 2026-11-06 by Utah Division of Water Rights: waterrights@utah.gov / 801-538-7240 is the public contact; https://waterrights.utah.gov/data-centers/ is accurate; OK to list publicly. The page names that address for city/county notice. Businesses can claim most report details confidential; the withdrawal amount stays public.",
   "sources": "https://waterrights.utah.gov/data-centers/ https://waterrights.utah.gov/",
   "update_contact_requested": "yes",
   "last_checked": "2026-11-06"
  },
  {
   "id": "va-hb496",
   "state": "VA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Virginia",
   "policy_type": "reporting",
   "summary": "HB 496 / SB 553 (2026): water suppliers that already report withdrawals must report monthly potable and reclaimed water delivered to data centers holding a DEQ air permit as separate totals; DEQ's amended rule (9VAC25-200) took effect Sept. 9, 2026.",
   "status": "in_force",
   "agency_name": "Virginia DEQ - Office of Water Supply",
   "agency_url": "https://www.deq.virginia.gov/water/water-quantity/water-supply-planning",
   "public_contact_email": "william.cloe@deq.virginia.gov",
   "public_contact_phone": "(804) 754-5457",
   "public_contact_notes": "Weedon Cloe, Office of Water Supply Manager, is listed as primary contact for the HB 496 rule on Virginia Regulatory Town Hall and on DEQ's water supply planning page.",
   "sources": "https://lis.blob.core.windows.net/files/1221621.PDF https://townhall.virginia.gov/l./ViewAction.cfm?actionid=7044 https://www.deq.virginia.gov/water/water-quantity/water-supply-planning",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "va-eo22",
   "state": "VA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Virginia",
   "policy_type": "other",
   "summary": "Budget language (HB 30, Item 366 #7c) has DEQ set 'cooling water scarcity area' criteria by July 1, 2027, and requires new data centers in the Eastern Virginia Groundwater Management Area that file a complete DEQ air permit application after Jan. 1, 2027 to use air cooling, closed-loop cooling or 100% recycled/stormwater; Executive Order 22 (Sept. 18, 2026) directs DEQ to speed that work.",
   "status": "in_force",
   "agency_name": "Virginia DEQ - Division of Water Planning",
   "agency_url": "https://www.deq.virginia.gov/water/water-quantity",
   "public_contact_email": "Elizabeth.McKercher@deq.virginia.gov",
   "public_contact_phone": "(804) 510-6112",
   "public_contact_notes": "Liz McKercher, Director, Division of Water Planning (listed on DEQ's Water Quantity page). Rulemaking is still to come; confirm which office will own it.",
   "sources": "https://www.governor.virginia.gov/media/governorvirginiagov/governor-of-virginia/pdf/eo/eo-22-establishing-va-data-center-accountability-and-ai-initiatives.pdf https://budget.lis.virginia.gov/amendment/2026/2/HB30/Enrolled/CR/366/7c/ https://www.deq.virginia.gov/water/water-quantity",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "va-loudoun",
   "state": "VA",
   "jurisdiction_level": "county",
   "jurisdiction_name": "Loudoun County",
   "policy_type": "local_zoning",
   "summary": "Since March 2025 new data centers need a special exception with a public hearing; under state law (Va. Code 15.2-2209.5) applicants must assess impacts on water resources, and a September 2026 draft plan/zoning amendment would require surface- and groundwater site assessments.",
   "status": "in_force",
   "agency_name": "Loudoun County - Data Centers: Water Considerations",
   "agency_url": "https://www.loudoun.gov/6402/Water-Considerations",
   "public_contact_phone": "703-777-0100",
   "public_contact_notes": "County government main line from the page footer; no data-center-specific email posted. Draft amendments CPAM-2025-0001 / ZOAM-2025-0002 are proposed, not adopted.",
   "sources": "https://www.loudoun.gov/6402/Water-Considerations https://www.loudoun.gov/DocumentCenter/View/222461/Draft-Data-Center-Standards-Project-Narrative-and-Amendment-Summary https://wjla.com/news/local/loudoun-county-adds-new-requirements-data-center-applications-energy-use-facilities-virginia-law-substations-impacts-water-resources-farmland-parks-historic-sites",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": ""
  },
  {
   "id": "va-prince-william",
   "state": "VA",
   "jurisdiction_level": "county",
   "jurisdiction_name": "Prince William County",
   "policy_type": "local_zoning",
   "summary": "A Data Center Opportunity Zone Overlay District steers data centers to areas with existing infrastructure; we found no county water-specific data center rule. State reporting (HB 496) and the state site-assessment law still apply.",
   "status": "unclear",
   "agency_name": "Prince William County - Zoning Administration",
   "agency_url": "https://www.pwcva.gov/department/zoning-administration/zoning-overlay-districts",
   "public_contact_notes": "No data-center water contact found on the overlay page. Next pass: county planning office contact.",
   "sources": "https://www.pwcva.gov/department/zoning-administration/zoning-overlay-districts",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "nj-plc75",
   "state": "NJ",
   "jurisdiction_level": "state",
   "jurisdiction_name": "New Jersey",
   "policy_type": "reporting",
   "summary": "P.L.2026, c.75 (S3379, signed Aug. 27, 2026): data centers must report total and peak daily water input and water sources (plus energy) to the Board of Public Utilities every six months for three years; BPU publishes within 30 days, with some details shielded from OPRA.",
   "status": "in_force",
   "agency_name": "New Jersey Board of Public Utilities (BPU)",
   "agency_url": "https://www.njeda.gov/datacenterta/",
   "public_contact_email": "Ombudsman@bpu.nj.gov",
   "public_contact_notes": "The state's Data Center Municipal Resource Hub (NJEDA) lists Ombudsman@bpu.nj.gov for BPU data center questions; BPU's own contact page uses a web form. First reports due Nov. 27, 2026 (centers operating a year or more) and Feb. 27, 2027 (others), per Day Pitney.",
   "sources": "https://www.njleg.state.nj.us/bill-search/2026/S3379 https://newjerseymonitor.com/2026/08/27/data-centers-water-energy-use-law/ https://www.njeda.gov/datacenterta/ https://www.daypitney.com/epc/article/print/12000",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_phone": ""
  },
  {
   "id": "az-adwr",
   "state": "AZ",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Arizona (Active Management Areas)",
   "policy_type": "withdrawal_permit",
   "summary": "Inside an Active Management Area, new non-exempt wells need ADWR approval tied to existing groundwater rights; Pima County's Project Blue wells were approved under three grandfathered rights (96.5 acre-feet a year) with annual use reports.",
   "status": "in_force",
   "agency_name": "Arizona Department of Water Resources - Groundwater Permitting & Wells",
   "agency_url": "https://www.azwater.gov/permitting-wells",
   "public_contact_email": "permit-wells@azwater.gov",
   "public_contact_phone": "(602) 771-8527",
   "public_contact_notes": "Phone on ADWR pages; the email is shown (obfuscated) on ADWR's well pages and listed in full by NGWA's Arizona resource page. ADWR main line (602) 771-8500.",
   "sources": "https://www.azwater.gov/permitting-wells https://www.azwater.gov/adwr-contact-us https://www.ngwa.org/connect-with-your-state/State-Resources/arizona https://news.azpm.org/p/environmentnews/2026/5/28/229919-arizona-water-officials-approve-wells-tied-to-project-blue-data-center/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "ga-epd",
   "state": "GA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Georgia",
   "policy_type": "withdrawal_permit",
   "summary": "An EPD permit is required to withdraw more than 100,000 gallons a day of groundwater; a data center on a city or county system is covered by that utility's permit instead.",
   "status": "in_force",
   "agency_name": "Georgia EPD - Watershed Protection Branch (water withdrawal permitting)",
   "agency_url": "https://epd.georgia.gov/water-withdrawal-permitting",
   "public_contact_email": "Christine.Voudy@dnr.ga.gov",
   "public_contact_phone": "470-607-2621",
   "public_contact_notes": "Listed contact for municipal and industrial groundwater withdrawals. Surface water: johmar.haye1@dnr.ga.gov, 470-604-9627. General: askepd@gaepd.org, Watershed Branch (404) 463-1511.",
   "sources": "https://epd.georgia.gov/water-withdrawal-permitting https://rules.sos.ga.gov/gac/391-3-2",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "ga-sb421",
   "state": "GA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Georgia",
   "policy_type": "disclosure",
   "summary": "SB 421 (2026) would bar local governments from NDAs that keep utilities from disclosing data center water and energy use; we could not confirm it became law.",
   "status": "unclear",
   "agency_name": "Georgia General Assembly",
   "public_contact_notes": "Next pass: confirm final status on legis.ga.gov.",
   "sources": "https://www.multistate.us/insider/2026/3/3/state-data-center-water-usage-legislation-gains-momentum",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "ga-newton-context",
   "state": "GA",
   "jurisdiction_level": "county",
   "jurisdiction_name": "Newton County (context)",
   "policy_type": "other",
   "summary": "Context, not policy: four families sued Meta in 2026 claiming construction at its Stanton Springs data center sent sediment into their wells; Meta disputes the claims.",
   "status": "unclear",
   "agency_name": "(court case; no agency contact)",
   "sources": "https://www.ajc.com/news/2026/09/georgia-families-sue-meta-accuse-its-data-center-of-tainting-their-water/ https://www.nytimes.com/2025/07/14/technology/meta-data-center-water.html",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": "",
   "public_contact_notes": ""
  },
  {
   "id": "mn-dnr",
   "state": "MN",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Minnesota",
   "policy_type": "withdrawal_permit",
   "summary": "A DNR water use permit is needed above 10,000 gallons a day or 1 million a year (city-supplied water is exempt); since 2025, data centers planning over 100 million gallons a year go through a DNR pre-application review, which is nonpublic.",
   "status": "in_force",
   "agency_name": "Minnesota DNR - Water use permits",
   "agency_url": "https://www.dnr.state.mn.us/waters/watermgmt_section/appropriations/permits.html",
   "public_contact_email": "info.dnr@state.mn.us",
   "public_contact_phone": "651-296-6157",
   "public_contact_notes": "General DNR info line and email from the permits page; water permitting and reporting staff: 651-259-5724. Area hydrologists handle local permits.",
   "sources": "https://www.dnr.state.mn.us/waters/watermgmt_section/appropriations/permits.html https://www.revisor.mn.gov/statutes/2025/cite/103G.265/subd/103G.265.5 https://www.house.mn.gov/hrd/as/94/2025-1/as012.pdf",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "or-dcac",
   "state": "OR",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Oregon",
   "policy_type": "other",
   "summary": "No statewide data center water law yet. Gov. Kotek's Data Center Advisory Committee held a water session in March 2026, took public comment through Oct. 24, 2026, and is drafting recommendations that include water reporting options.",
   "status": "proposed",
   "agency_name": "Oregon Department of Energy - Data Center Advisory Committee",
   "agency_url": "https://www.oregon.gov/energy/get-involved/pages/oregon-data-center-advisory-committee.aspx",
   "public_contact_email": "datacenter.ac@oregon.gov",
   "public_contact_phone": "503-378-4040",
   "public_contact_notes": "The committee page says to email datacenter.ac@oregon.gov to sign up for updates. ODOE general: AskEnergy@energy.oregon.gov.",
   "sources": "https://www.oregon.gov/energy/get-involved/pages/oregon-data-center-advisory-committee.aspx https://www.oregon.gov/energy/get-involved/Documents/2026-09-10-DCAC-Preliminary-Learnings.pdf",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "or-the-dalles",
   "state": "OR",
   "jurisdiction_level": "county",
   "jurisdiction_name": "The Dalles (city)",
   "policy_type": "disclosure",
   "summary": "Google's data centers are The Dalles' largest water customers; the city now releases historical use, but future-use projections remain confidential, per The Oregonian.",
   "status": "unclear",
   "agency_name": "City of The Dalles",
   "public_contact_notes": "City contact not verified this pass.",
   "sources": "https://www.oregonlive.com/silicon-forest/2026/04/more-oregon-water-for-googles-data-centers-more-concern-over-secrecy.html https://sustainability.google/files/google-2026-environmental-report.pdf",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "fl-marion",
   "state": "FL",
   "jurisdiction_level": "county",
   "jurisdiction_name": "Marion County",
   "policy_type": "moratorium_pause",
   "summary": "12-month moratorium (adopted Sept. 15, 2026) on rezonings, permits and site plans for data centers with 50 MW or more peak load in unincorporated Marion County while staff study Floridan Aquifer withdrawals, utilities, springs and cooling.",
   "status": "in_force",
   "agency_name": "Marion County Public Relations (Growth Services study)",
   "agency_url": "https://www.marionfl.org/agencies-departments/departments-facilities-offices/growth-services/planning-zoning/data-centers",
   "public_contact_email": "PublicRelations@MarionFL.org",
   "public_contact_phone": "352-438-2300",
   "public_contact_notes": "Confirmed 2026-11-06 by Chuck Varadin (Growth Services Director): Public Relations is the public contact for moratorium and water-use RFIs (PublicRelations@MarionFL.org / 352-438-2300); OK to list. County data-centers page: https://www.marionfl.org/agencies-departments/departments-facilities-offices/growth-services/planning-zoning/data-centers.",
   "sources": "https://marionfl.legistar.com/LegislationDetail.aspx?GUID=DD43C2FF-7419-4A73-B9BD-2A08F89914E0&ID=8205988&Options=&Search= https://www.ocala-news.com/2026/09/16/marion-county-approves-12-month-moratorium-on-large-scale-data-centers/ https://www.marionfl.org/agencies-departments/departments-facilities-offices/growth-services/planning-zoning/data-centers",
   "update_contact_requested": "yes",
   "last_checked": "2026-11-06"
  },
  {
   "id": "fl-levy",
   "state": "FL",
   "jurisdiction_level": "county",
   "jurisdiction_name": "Levy County",
   "policy_type": "moratorium_pause",
   "summary": "Ordinance 2026-05 halts data center applications in unincorporated Levy County through Sept. 30, 2027 while staff study Floridan Aquifer, groundwater, cooling, wastewater and drought impacts.",
   "status": "in_force",
   "agency_name": "Levy County Board of County Commissioners",
   "public_contact_notes": "County contact not verified this pass.",
   "sources": "https://mccmeetingspublic.blob.core.usgovcloudapi.net/levyfl-meet-a106d2b40d91493fa736cfe8000ff12d/ITEM-Attachment-001-99388d3b2241462a89283a4bf8118270.pdf https://www.chronicleonline.com/news/local/levy-county-approves-moratorium-on-data-centers/article_177dad48-7ddc-55b8-a945-cedb2a3a0013.html",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "fl-sjrwmd",
   "state": "FL",
   "jurisdiction_level": "district",
   "jurisdiction_name": "St. Johns River Water Management District",
   "policy_type": "withdrawal_permit",
   "summary": "A data center pumping its own groundwater or surface water in the district (which includes much of Marion County) needs a Consumptive Use Permit.",
   "status": "in_force",
   "agency_name": "St. Johns River WMD - Permitting",
   "agency_url": "https://www.sjrwmd.com/permitting/contacts/",
   "public_contact_email": "permitting@sjrwmd.com",
   "public_contact_phone": "386-329-4570",
   "public_contact_notes": "Confirmed 2026-11-17 by Shannon Barican (Regulatory Support Manager): listed contact is correct (permitting@sjrwmd.com / 386-329-4570). Preferred way to check Consumptive Use Permit status is the ePermit Portal (https://permitting.sjrwmd.com/ep/#/ep; Search menu covers CUP applicants/permits and compliance items). Permitting rules and documents: https://www.sjrwmd.com/documents/permitting/. Contact is the backup for questions.",
   "sources": "https://www.sjrwmd.com/permitting/contacts/ https://permitting.sjrwmd.com/ep/#/ep https://www.sjrwmd.com/documents/permitting/",
   "update_contact_requested": "yes",
   "last_checked": "2026-11-17"
  },
  {
   "id": "fl-swfwmd",
   "state": "FL",
   "jurisdiction_level": "district",
   "jurisdiction_name": "Southwest Florida Water Management District",
   "policy_type": "withdrawal_permit",
   "summary": "An individual water use permit is needed at 100,000 gallons a day (annual average), 1 million gallons a day of capacity, or a well 6 inches or wider.",
   "status": "in_force",
   "agency_name": "Southwest Florida WMD - Water Use Permit",
   "agency_url": "https://www.swfwmd.state.fl.us/business/epermitting/water-use-permit",
   "public_contact_notes": "Contact not verified this pass.",
   "sources": "https://www.swfwmd.state.fl.us/business/epermitting/water-use-permit https://www.law.cornell.edu/regulations/florida/Fla-Admin-Code-Ann-R-40D-2-041",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "ia-general",
   "state": "IA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Iowa",
   "policy_type": "withdrawal_permit",
   "summary": "No data-center-specific water rule enacted: HF 2690 (formerly HF 2447), which would have required quarterly data center water reports to DNR, died when the session ended May 3, 2026. A DNR water use permit is required to withdraw 25,000 gallons or more in a day.",
   "status": "in_force",
   "agency_name": "Iowa DNR - Water Allocation & Use",
   "agency_url": "https://www.iowadnr.gov/environmental-protection/water-quality/water-supply-engineering/water-allocation-use",
   "public_contact_email": "Michael.Anderson@dnr.iowa.gov",
   "public_contact_phone": "515-725-0336",
   "public_contact_notes": "Michael Anderson, P.E., Senior Environmental Engineer, listed on the water allocation page (also the contact for well interference guidance). DNR customer service 515-725-8200.",
   "sources": "https://www.iowadnr.gov/environmental-protection/water-quality/water-supply-engineering/water-allocation-use https://www.legis.iowa.gov/legislation/billTracking/billHistory?billName=HF2690&ga=91 https://dailyiowan.com/2026/11/02/iowa-lawmakers-candidates-discuss-data-center-policies-ahead-of-election/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "oh-general",
   "state": "OH",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Ohio",
   "policy_type": "withdrawal_permit",
   "summary": "No data-center-specific water rule enacted (HB 784 and SB 378, filed March 2026, were still proposals when last tracked). Facilities able to withdraw over 100,000 gallons a day must register with ODNR and report yearly; large new consumptive uses may need a high-capacity permit.",
   "status": "in_force",
   "agency_name": "ODNR Division of Water Resources - Withdrawal Reporting & Facility Registration",
   "agency_url": "https://ohiodnr.gov/discover-and-learn/safety-conservation/about-odnr/water-resources/water-inventory-planning/withdrawal-reporting-facility-registration/withdrawal-reporting-facility-registration",
   "public_contact_email": "Bradley.Lodge@dnr.ohio.gov",
   "public_contact_notes": "ODNR's registration page names Bradley Lodge for high-capacity permitting questions.",
   "sources": "https://ohiodnr.gov/discover-and-learn/safety-conservation/about-odnr/water-resources/water-inventory-planning/withdrawal-reporting-facility-registration/withdrawal-reporting-facility-registration https://codes.ohio.gov/ohio-revised-code/section-1521.16 https://savrn.com/blog/data-center-water-tracker-update-2026-09-23",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_phone": ""
  },
  {
   "id": "in-general",
   "state": "IN",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Indiana",
   "policy_type": "withdrawal_permit",
   "summary": "No data-center-specific water rule enacted (HB 1043, a DNR data center consumption permit, failed in 2026). Facilities able to pump over 100,000 gallons a day must register with DNR and report yearly.",
   "status": "in_force",
   "agency_name": "Indiana DNR Division of Water",
   "agency_url": "https://www.in.gov/dnr/water/contact-us/",
   "public_contact_phone": "317-232-4160",
   "public_contact_notes": "Contact page uses an 'Email Division of Water' form; toll-free 1-877-928-3755. The division sends correspondence from water_inquiry@dnr.IN.gov.",
   "sources": "https://www.in.gov/dnr/water/contact-us/ https://www.in.gov/dnr/water/water-availability-use-rights/significant-water-withdrawal-facility-registration/ https://lcssp.caltech.edu/documents/34479/Annotated_state_legislation_on_data_center_reporting.pdf https://savrn.com/blog/data-center-water-tracker-update-2026-09-23",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": ""
  },
  {
   "id": "nc-general",
   "state": "NC",
   "jurisdiction_level": "state",
   "jurisdiction_name": "North Carolina",
   "policy_type": "withdrawal_permit",
   "summary": "No statewide data-center-specific water rule enacted (SB 730, which would set DEQ water standards and ban evaporative cooling, was proposed June 2026). In 15 Central Coastal Plain counties, groundwater use over 100,000 gallons a day needs a permit.",
   "status": "in_force",
   "agency_name": "NC DEQ Division of Water Resources - CCPCUA",
   "agency_url": "https://www.deq.nc.gov/about/divisions/water-resources/groundwater-resources/central-coastal-plain-capacity-use-area-ccpcua-water-withdrawal-permit",
   "public_contact_notes": "DEQ links a CCPCUA staff-contacts list; no single public email confirmed this pass.",
   "sources": "https://www.deq.nc.gov/about/divisions/water-resources/groundwater-resources/central-coastal-plain-capacity-use-area-ccpcua-water-withdrawal-permit https://savrn.com/blog/data-center-water-tracker-update-2026-09-23",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "sc-general",
   "state": "SC",
   "jurisdiction_level": "state",
   "jurisdiction_name": "South Carolina",
   "policy_type": "withdrawal_permit",
   "summary": "No data-center-specific water rule enacted (S.724 water-use reports failed; HB 4583 closed-loop mandate was proposed). Groundwater use over 3 million gallons a month needs a permit in Capacity Use Areas and registration elsewhere.",
   "status": "in_force",
   "agency_name": "SC Department of Environmental Services - Groundwater Use Reporting",
   "agency_url": "https://des.sc.gov/programs/bureau-water/groundwater-management-planning/groundwater-use-reporting",
   "public_contact_email": "info@des.sc.gov",
   "public_contact_phone": "(803) 898-3432",
   "public_contact_notes": "Agency general contact from the page footer; Leigh Anne Monroe, (803) 898-2415, is named for water use reports.",
   "sources": "https://des.sc.gov/programs/bureau-water/groundwater-management-planning/groundwater-use-reporting https://www.multistate.us/insider/2026/3/3/state-data-center-water-usage-legislation-gains-momentum https://savrn.com/blog/data-center-water-tracker-update-2026-09-23",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "la-general",
   "state": "LA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Louisiana",
   "policy_type": "withdrawal_permit",
   "summary": "No data-center-specific water rule enacted (HB 1206 on data center water permitting and reporting failed April 2026). Groundwater use falls under the state Ground Water Resources Program.",
   "status": "in_force",
   "agency_name": "Louisiana Ground Water Resources Program (Office of Conservation)",
   "agency_url": "https://denr.louisiana.gov/page/gwr-program-page",
   "public_contact_email": "Gwater@la.gov",
   "public_contact_phone": "(225) 342-8244",
   "public_contact_notes": "From the program page, which now sits on an archive site after the department was reorganized (Department of Conservation and Energy); confirm the address still routes. Page asks you to name the parish.",
   "sources": "https://denr.louisiana.gov/page/gwr-program-page https://tulanewater.org/wp-content/uploads/2026/09/Issue-Brief-Louisiana-Data-Centers-and-Water-Management-FINAL.pdf https://savrn.com/blog/data-center-water-tracker-update-2026-09-23",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06"
  },
  {
   "id": "pa-act21",
   "state": "PA",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Pennsylvania",
   "policy_type": "reporting",
   "summary": "Act 21 of 2026 (Fiscal Code Article XVIII-B) requires data centers with 10 MW or more peak demand to file annual energy and water consumption reports with DEP; first reports due July 1, 2027.",
   "status": "in_force",
   "agency_name": "Pennsylvania DEP",
   "public_contact_notes": "DEP contact for these reports not verified this pass.",
   "sources": "https://www.palegis.us/statutes/unconsolidated/law-information/view-statute&txtType=PDF&SessYr=1929&SessInd=0&ActNum=0176.&chpt=018B&subchpt=000.&sctn=013.&subsctn=000. https://www.altoonamirror.com/news/local-news/2026/07/pa-ai-datacenters-state-keeps-tabs/",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  },
  {
   "id": "id-h895",
   "state": "ID",
   "jurisdiction_level": "state",
   "jurisdiction_name": "Idaho",
   "policy_type": "withdrawal_permit",
   "summary": "H 895 (signed April 2, 2026; effective July 1, 2026) bars data centers that begin construction after that date from consumptive use of water for cooling unless it comes from a municipal or water/sewer district system.",
   "status": "in_force",
   "agency_name": "Idaho Department of Water Resources",
   "public_contact_notes": "IDWR contact not verified this pass.",
   "sources": "https://legislature.idaho.gov/sessioninfo/2026/legislation/h0895/ https://legislature.idaho.gov/wp-content/uploads/sessioninfo/2026/legislation/H0895.pdf",
   "update_contact_requested": "no",
   "last_checked": "2026-11-06",
   "agency_url": "",
   "public_contact_email": "",
   "public_contact_phone": ""
  }
 ]
}